Production Performance Brief

FAT and SAT Performance Acceptance for Bottling Lines

Performance acceptance is only clear when the test basis, evidence and responsibilities are agreed before the test begins.

Direct answer

What should a bottling-line performance test prove?

It should show how the confirmed equipment or connected line performs with the agreed SKU, inputs, duration, operating conditions and good-output boundary.

Review point 01

Freeze the test basis

Document the reference bottle, closure, label, pack, product or test medium, utilities and staffing before FAT or SAT.

  • Approved samples and drawings
  • Material quantity and condition
  • Test duration
  • Rated and accepted output definitions

Review point 02

Record more than the final counter

Capture gross output, good output, rejects, stops, interventions and relevant operating conditions.

  • Start and finish time
  • Stop reason and duration
  • Rejected quantity
  • Good output at agreed boundary

Review point 03

Close the test transparently

Record passed items, limitations and remaining actions with owners and due dates. A conditional result should not be presented as an unconditional pass.

  • Signed test record
  • Open-item list
  • Retest condition
  • Document handover

Questions before specification

Frequently asked questions

Answers are planning guidance. Project requirements and performance remain subject to confirmed data and agreements.

Are FAT and SAT the same test?

No. FAT is performed before shipment within an agreed factory scope; SAT checks the installed system under confirmed site conditions.

Should changeover be part of acceptance?

Include it when it is within the purchased scope and commercial agreement, with approved formats and a clear timing boundary.